July 31, 2017
The manufacturing of nuclear reactor components: quality and nuclear safety at the heart of a large-scale plan for Creusot Forge
The AREVA NP facility at Le Creusot is one of the only facilities in the world capable of producing the large forged parts required for the power plants nuclear islands. Since the launch of civil nuclear programs in the 1970s, the facility has supplied some 3,000 forgings and castings for the reactor coolant systems of nuclear facilities all around the world.
In April 2015, following the detection of methodological discrepancies in the performance of tensile tests conducted during the manufacturing process, AREVA NP decided to launch a comprehensive quality audit at the Le Creusot site. This audit brought to light irregularities in the manufacturing records at the site. AREVA NP then reinforced the control and the traceability of the operations in progress, implementing double-checking of documentation and measures relating to the transcription of documents.
With inputs including the analysis of the causes of these irregularities and reports compiled by third parties such as the independent audit firm Lloyds Register Apave, a global improvement plan was drawn up by the Creusot Forge teams. Its deployment, begun in 2016, continues through 2017.
This plan has two main objectives:
- To identify the causes of the past irregularities and non-compliant practices;
- To restore the quality system to full efficacy and establish effective control of production processes.
The purpose of this plan for AREVA NP is to restore the confidence of its customers, the different safety authorities around the world and all other stakeholders, and consolidate Creusot Forge's place among the worldwide references in the nuclear forging industry.
The 220 employees who work there are fully mobilized to implement the improvement plan. Each one of them, in their own area, is committed to stepping up the nuclear safety and quality of the components produced at the site.
70% of the actions in the plan underway at Creusot Forge have been completed by July 2017.
All of the necessary actions aimed at resuming forging operationsfor the project to supply two EPR reactors to the UK have been put in place. On-site reviews and inspections have taken place regularly to provide information for the customer, NNB, and the UK safety authority, the Office for Nuclear Regulation (ONR), on progress made on all these actions. Test parts - two primary legs and a steam generator nozzle shell - were forged in March and June 2017 to substantiate the operational, organizational and technical control delivered by the measures put in place under the plan. A detailed review in mid-June provided the basis for setting milestones for the resumption of production.
Creusot Forge's customers in France and abroad, as well as all the safety authorities concerned, are being kept regularly informed of the actions undertaken at the site.
-
Press releases
- June 19, 2017: AREVA NP reviews Le Creusot plant quality improvement plan with its customers EDF and NNB
- March 31, 2017: Le Creusot status update
- March 1, 2017: update on the audit in progress at the time of publication of annual results
- January 13, 2017: press visit to Le Creusot
- September 23, 2016: completion of analysis of marked records
- July 19, 2016: analyses continuing on a component of a steam generator at Fessenheim 2
- June 30, 2016: status update at end of June
- May 31, 2016: status update at end of May
- April 29, 2016: status update at end of April
- December 15, 2015: presentation of the quality plan for the Le Creusot plant
- April 21, 2015: analyses underway at the Le Creusot site regarding the quality of forged parts and the quality system
-
Hearings, inspections, discussions with the regulator ASN on the action in progress at the Le Creusot site
- May 12, 2017: letter from AREVA NP regarding resumption of production for BNI's within Creusot Forge (letter ref. ARV-DEP-00730)
- May 11, 2017: AREVA NP presentation of the AREVA NP Creusot Forge improvement plan (CMHCQ2017033)
- May 9, 2017: summary by AREVA NP of the analysis and integration of recommendations issued by the nuclear safety authorities and independent bodies (note CMHCQ2017039)
- April 12, 2017: ASN letter regarding resumption of forging operations on components intended for basic nuclear installations within Creusot Forge
- March 31, 2017: letter from AREVA NP in response to the requirements set out in the follow-up letter dated January 31, 2017 (letter ARV-DEP-00686)
- January 31, 2017: follow-up letter relating to the multinational inspection conducted from November 28 to December 2, 2016 at the Creusot Forge site
- August 22, 2016: incident report relating to irregularities detected in manufacturing records at Le Creusot (in French)
- August 11, 2016: follow-up letter relating to the inspection conducted on July 20, 2016 at the Le Creusot site
- August 1, 2016: letter from AREVA NP relating to the quality action plans at these manufacturing sites, including actions to identify and process findings Letter ARV-DEP-0544
- July 28, 2016: follow-up letter relating to the inspection conducted on July 5, 2016 at the Le Creusot site
- July 18, 2016: memo regarding the suspension of the test certificate on a steam generator installed on reactor 2 of the Fessenheim nuclear power plant.
- May 23, 2016: follow-up letter relating to the inspection conducted on May 3 and 4, 2016 at the Le Creusot site
- May 9, 2016: follow-up letter relating to inspections conducted on January 20 and 22, 2016 at the Le Creusot site
-
Appearances before the High Committee For Transparency and Information on Nuclear Security (Haut comité pour la transparence et l'information sur la sécurité nucléaire – HCTISN)
- October 5, 2017 : AREVA NP’presentation related to Le Creusot site quality audit and plan in HCTISN plenary meeting:
- See AREVA NP’s presentation (in French only)
- Go to HCTISN’s website: http://www.hctisn.fr (in French only)
- November 23, 2016: visit to the Le Creusot site by a delegation from the HCTISN
- June 30, 2016: meeting relating to quality audits at the Le Creusot site: link to the special page on the HCTISN site (in French)
- October 5, 2017 : AREVA NP’presentation related to Le Creusot site quality audit and plan in HCTISN plenary meeting:
-
Appearance before to the French Parliamentary Office for the Evaluation of Scientific and Technological Choices (Office Parlementaire d'Évaluation des Choix Scientifiques et Technologiques – OPECST)
- October 25, 2016: appearances by Bernard Fontana, CEO of AREVA NP, and David Emond, Head of the AREVA NP Components Business Unit, concerning the safety of nuclear pressure equipment
-
General nuclear review (published by the French Nuclear Energy Society – SFEN)
- March-April 2017 issue: file on the fabrication of heavy equipment at the Le Creusot site (in french)